expansion tank to 25 psi. If the pressure is higher bleed
pressure out until it is correct. If the pressure is too low
add air by use of a compressor or bicycle pump until
the pressure is correct.

12. Plumb the solar pump station to the storage tank

and to the collector: The tank connections should
use ¾” copper pipe and can be connected using
the threaded adaptors provided. The collector
connections should use ½” copper pipe and can be
connected with the compression fittings provided.
The total piping run in the solar loop should not exceed
200 equivalent feet. Failure to limit the line length may
cause poor system performance and lead to premature
pump failure.

13. Add the supplied copper drain valve to the lowest point

in the collector loop (near the tank by the bottom coil
outlet labeled “to pump” in most cases)

14. Install a discharge pipe to the pump station relief valve

that must terminate a maximum of six inches above a
floor drain or external to the building.

Installing the ½” copper to and from the collector using
the compression fittings.

1. Push the union nut

and

the cutting ring

onto the

copper pipe

. The pipe

must protrude at least 3/8”
(3 mm) from the cutting ring
in order to ensure the force
transmission and the sealing.

2. Insert the support sleeve

into

the copper pipe.

3. Insert the copper pipe with the

plugged-on individual parts (

,

and

) all the way into the

housing of the compression
fitting

.

4. First screw the union nut

manually.

5. Tighten the union nut

by

rotating one full turn. Hold the
housing of the compression
fitting

to avoid rotation in order

to avoid damaging the sealing
ring.

Figure 27.

PLUMBING CONFIGURATION

V

L

H

K

1

2

3

4

1. ½” copper tube - from

the collector outlet
(top) to the collector
return compression
fitting (K)

2. ½” copper tube – from

t h e c o l l e c t o r i n l e t
(bottom) to the collector
supply compression
fitting (L)

3. ¾” copper tube – from

the upper tank coil
inlet marked “from
collector” to the tank
supply threaded fitting
(H)

4. ¾ ” c o p p e r t u b e –

from the lower tank
coil outlet marked
“to pump” to the tank
return threaded fitting
(V)

Figure 28.

FUNCTION

Check valves

The solar station is equipped with check valves in the supply
and the return ball valve (J, Q).

For filling, venting and flushing of the installation the check
valves must be turned to the correct position. To set the
proper position for the check valves take off the temperature
gauges (C, E), remove the top cover (D) and turn the ball
valves into the proper position using a wrench. See Figure
29. In the 45° position the balls in the ball valves push the
check valves open.

During operation the ball valves must be in 0° position.

45°

90°

Check valve is
operating, flow
only in flow
direction

Check valve is not
operating, flow in
both directions.

Ball valve
closed,
no flow.