Chapter 3: mechanical installation, 1 overview, 2 mounting requirements – Horner APG XL7 OCS User Manual

Page 16: 1 mounting procedures (installed in a panel door)

Advertising
background image

XL7 User Manual

CHAPTER 3: MECHANICAL INSTALLATION

Note: The datasheet is the first document to refer to for model-specific information related to XL7

OCS models such as pin-outs, jumper settings, and other key installation information. Visit the Horner

websites to obtain datasheets, user documentation, and updates.

3.1

Overview

The mechanical installation greatly affects the operation, safety and appearance of the system.

Information is provided to mechanically install the unit such as cut-out sizes, mounting procedures and

other recommendations for the proper mechanical installation of the unit.

3.2 Mounting Requirements

3.2.1 Mounting Procedures (Installed in a Panel Door)

Figure 3.1 – Panel Mounting of an XL7 Series OCS

Once the panel design has been completed using the criteria and suggestions in the following sections,

use the following steps to panel mount the XL7 OCS.

1. Remove all connectors from the XL7 OCS unit.

2. Make sure the gasket is installed on the XL7 OCS and is free from dust and debris. Check that the

corners of the gasket are secure.

3. Pass the unit through the panel.

4. Insert each of the four (4) mounting clips into the slots in the XL7 OCS case. One clip should be

installed on each corner. Lightly tighten each screw so the clip is held in place.

5. Tighten the screws on the clips such that the gasket is compressed against the panel. Recommended

torque is 7-10 lb/in (0.8-1.13 Nm.)

Page 16 of 110

Advertising