Signal conditioners, Programmable controller – L.B. White FA-MCS-D User Manual

Page 16

Advertising
background image

Signal conditioners receive 24 VAC from the lower
transformer in the SmartBox

, in addition to a

4-20 mA input signal from the programmable
controller.

The conditioner sends anywhere from 0-15 VDC to
the heater’s variable rate gas control for operation,
based upon the 4-20 mA signal supplied from the
programmable controller.

See Fig.39 for reference to terminals on the
conditioner when checking voltage and connection
of wiring.

FIG.39

SIGNAL CONDITIONERS

The controller requires 24 VAC for operation which can
be checked at the terminals shown in Fig 37.
(Without 24 VAC, the controller will not operate the
SmartBox

)

FIG. 37

The controller also includes an LED which provides
operation status. When power is applied, the LED may
appear in one of the conditions given in the following
table:

:

Replacement
a. Remove all individual wires from the terminal

blocks and reconnect to the replacement
controller

or

b. Remove the terminal blocks with the wiring intact

from original controller and transfer the blocks to
the replacement controller

If transferring the blocks with wiring intact, refer to the
following:
a. Use a thin bladed screw driver to evenly raise the

block from its alignment pins on the replacement
controller.

b. Insert the screwdriver blade no more than 1/8 in. to

prevent damage to the alignment pins.

c. Insert the screwdriver blade at one end of the

terminal block and rotate the blade about 1/4
turn.

d. Move to the other end of the terminal block and

do the same. See Fig.38. Repeat the process until
the block is evenly raised about 1/4 in. from the
alignment pins.

e. Once the block has been elevated, grasp the

block at its center and carefully pull the block
straight up.

f. Complete these same steps for removal of the

blocks with wiring from the original controller.

g. Remove respective blocks from replacement

controller using this process.

h. Transfer the blocks with wiring to the replacement:

-- Position the block onto the respective

alignment pins.

-- Press straight down to firmly seat the

block.

-- Repeat the process for all blocks.

FIG. 38

PROGRAMMABLE CONTROLLER

24 VAC INPUT FROM UPPER TRANSFORMER

LED

16

24 VAC INPUT
FROM LOWER
TRANSFORMER

0-15 VDC OUTPUT
TO GAS CONTROL

4-20 mA INPUT
FROM CONTROLLER

OFF

Not applicable

No power to controller,
low voltage, or controller
damaged

ON

ON steady

Not blinking

Controller is receiving
power but its internal
processor has
malfunctioned.

Very slow blink
(continuous)

1 second ON
1 second OFF

Normal operation

Slow blink
(continuous)

0.5 second ON
0.5 second OFF

Sensor failure

LED

BLINK RATE

STATUS