Transporting a load, Leveling procedure, Transporting a load -5 leveling procedure -5 – JLG 4017RS Operator Manual User Manual

Page 69

Advertising
background image

Section 4 - Operation

4-5

31200938

Transporting a Load

• After engaging the load and resting it against the backrest, tilt the load back to

position it for travel. Travel in accordance with the requirements set forth in Section
1 - General Safety Practices
and Section 5 - Attachments.

Leveling Procedure

1. Position machine in best location to lift or place load.

2. Apply parking brake and shift transmission to NEUTRAL.

3. Observe level indicator(s) to determine whether machine must be leveled prior to

lifting load. If equipped, level machine with frame level switch (see page 3-20) or
outrigger controls (see page 3-15 or 3-18).

4. Move boom/attachment to 1,2 m (4 ft) off ground.

(AUS - Move boom so forks are no more than 300 mm (11.8 in) above ground
surface.)

Important things to remember:

• Never raise the boom/attachment more than 1,2 m (4 ft) above ground unless

telehandler is level.
(AUS - Never raise the forks more than 300 mm (11.8 in) above ground surface unless
telehandler is level.)

• The combination of frame leveling and load could cause the telehandler to tip over.

OW0540