SECTION 2 - PROCEDURES

3121801

– JLG Lift –

2-5

Cylinders w/Single Counterbalance Valves -
Lift Cylinder

OPERATE ALL FUNCTIONS FROM GROUND CONTROL STATION
ONLY.

1. Using all applicable safety precautions, activate

hydraulic system.

WHEN WORKING ON THE LIFT CYLINDER, RAISE THE PLAT-
FORM COMPLETELY AND SUPPORT THE PLATFORM USING A
SUITABLE OVERHEAD LIFTING DEVICE.

DO NOT FULLY EXTEND LIFT CYLINDER TO END OF STROKE.
RETRACT CYLINDER SLIGHTLY TO AVOID TRAPPING PRES-
SURE.

2. Raise platform completely then retract cylinder

slightly to avoid trapping pressure. Place a suitable
overhead lifting device approximately 2.5 cm (1 in)
below the platform.

3. Shut down hydraulic system and allow machine to

sit for 10-15 minutes. Carefully remove hydraulic
hoses from cylinder port block.

4. There will be initial weeping of hydraulic fluid, which

can be caught in a suitable container. After the initial
discharge, there should not be any further leakage
from the ports. If leakage continues at a rate of 6-8
drops per minute or more, the counterbalance valve
is defective and must be replaced.

5. If no repairs are necessary or when repairs have

been made, carefully reconnect hydraulic hoses to
the appropriate ports.

6. Remove lifting device from platform, activate hydrau-

lic system and run cylinder through one complete
cycle to check for leaks.

2.9 LIFT CYLINDER REMOVAL AND

INSTALLATION

Removal

1. Place the machine on a flat and level surface. Start

the motor and raise the platform. Shut down the
engine and attach a suitable lifting device to the plat-
form.

2. Remove the bolt and locknut securing the cylinder

rod attach pin to the upper inner arm assembly.
Using a suitable brass drift, drive out the rod end
attach pin from the arm assembly.

3. Retract the lift cylinder rod completely.

4. Tag and disconnect the hydraulic lines, then cap the

lift cylinder hydraulic lines and ports.

5. Remove the bolt and locknut securing the barrel end

attach pin to the lower arm assembly. Using a suit-
able brass drift, drive out the barrel end attach pin
from the arm assembly.

6. Carefully remove the cylinder from the scissor lift

and place in a suitable work area.

Installation

1. Install lift cylinder in place using suitable slings,

aligning barrel end attach pin mounting holes on
lower arm assembly.

2. Using a suitable drift, drive the barrel end attach pin

through the mounting holes in the lift cylinder and
the lower arm assembly. Secure in place with the
bolt and locknut.

3. Remove cylinder port plugs and hydraulic line caps

and correctly attach lines to cylinder ports.

4. Extend the cylinder rod until the attach pin hole

aligns with those in the upper arm assembly. Using a
suitable drift, drive the cylinder rod attach pin
through the aligned holes, taking care to align the
pin retaining hole with the hole in arm assembly.
Secure the pin in place with the bolt and locknut.

5. Lower platform to stowed position and shut down

motor. Check hydraulic fluid level and adjust accord-
ingly