SECTION 2 - PROCEDURES

3120864

– JLG Lift –

2-65

NOTE: Earlier models did not use retaining ring (22).

10.

Remove retaining ring (22) and bearing (19) from
shaft (10).

11.

Press Rotary oil seal (23) from housing (21).

Cleaning and Inspection

1.

Clean all parts thoroughly.

2.

Closely inspect all parts for excessive wear, cracks,
and chips. Replace parts as necessary.

3.

Discard seals and o-rings.

4.

Closely inspect bearings and bearing contact sur-
faces. Replace as necessary.

NOTE: Bearings may be reused if, after thorough inspection,

they are found to be in good condition.

Assembly

NOTE: Lubricate all seals and o-rings with clean hydraulic

oil prior to assembly.

1.

Clean all parts thoroughly before assembly.

2.

Press new rotary oil seal (23) into housing (21). Note
direction of the seal.

NOTE: Earlier models did not use retaining ring (22).

3.

Install new bearing (19) and retaining ring (22) on
shaft (10).

4.

Insert shaft assembly and retaining ring (18) in hous-
ing (21).

NOTE: Be sure to use the same number of springs and

spring pattern as recorded during disassembly.
Spring retainer (17) was not used in earlier models.

5.

Insert dowel pins (20), spring retainer (17) and
springs (15 & 16) in housing (21).

6.

Position new large diameter return plate (14) in
housing with tabs guided by dowel pins (20) until
disc rests on springs (15 & 16).

DISCS (11, 14) AND FRICTION DISCS (12) SHOULD REMAIN DRY
DURING INSTALLATION. NO OIL RESIDUE SHOULD BE ALLOWED
TO CONTAMINATE DISC SURFACES.

7.

Place a new friction disc (12) on shaft (10) until it
contacts return plate (14).

8.

Add additional new discs (11) and new friction discs
(12) as required to complete assembly.

9.

Insert separators (13) in holes of return plate.

10.

Install new o-ring (5), new backup ring (6), new o-
ring (8) and new back-up ring (9) on piston (7). Note
order of o-rings and back-up rings. Insert piston (7)
into end cover (2) being careful not to shear o-rings
or back-up rings.

11.

Install new case seal (4) in housing (21) then install
bleeder screw (3) in end cover (2).

12.

Position end cover (2) on housing (21) aligning
dowel pins (20) with holes in end cover.

NOTE: If available, a hydraulic press will simplify installation

of end cover on housing. Clamp cover in position
while tightening capscrews.

13.

Press on inner ring of bearing (37) until it shoulders
on shaft (45) to eliminate binding on bearings. Be
certain to restrain opposite end of shaft to avoid
excessive thrust loading on bearing (54).

IF HYDROSTATIC BENCH TESTING IS PERFORMED ON THE
BRAKE ASSEMBLY, RELEASE PRESSURE SHOULD NOT EXCEED
138 BAR UNLESS TWO ADDITIONAL BOLTS ARE USED FOR SUP-
PLEMENTAL CLAMPING.

2.24 DRIVE BRAKE - AUSCO - MACHINES

BUILT PRIOR TO MARCH 1992

Disassembly

1.

With shaft protrusion downward, remove bolts (21)
alternately, power plate (20) and gasket 2.

2.

Bearing (18) is pressed onto shaft (7) and must be
removed before removal of rotating discs (11) and
stationary discs (12).

3.

Remove shaft and stack subassembly from housing
by lightly tapping or pressing on the small external
spline end of the shaft and removing the shaft, bear-
ings and stack from the housing (1).

4.

Remove bearing (18), stationary discs (12), rotating
discs (11), springs (10) and primary disc 9.

5.

Remove bearing (3) from shaft, using care not to
damage seal 4. Remove seal and inspect sealing lip
and OD for damage. If damaged, replace per reas-
sembly instructions.

6.

Remove springs (6) and spring retainer (5) from
housing (1).

7.

Remove piston (13) from power plate by introducing
low pressure air (15 psi [1 Bar]) into the hydraulic
inlet. Make sure piston is directed away from the

Advertising