3 Sites of installation

3.1 Key factors of operation


There are four key issues that the site survey has to shed light on. Proper system
operation cannot be guaranteed without satisfying all of the four requirements.

Clear line of sight

- The entire optical path between the two ends must be free

of any obstacles. It not only means that one has to see the other side, but other
possible sources of disturbance should also be taken into consideration. For
example there might be turbulence above the roofs and other constructions, and this
can cause fraction or scattering of th
close to the beam can influence or even interrupt communication.

Solid mount surface

-

the beam is limited, it is extremely important to mount the unit on a
with the possible smallest movement. This way the receiver of the remote unit
cannot get out of the beam due to the movement of the opposite head.

East-West orientation

filters to protect the receiver diode from the effect of undesired light sources, direct
sunshine can cause saturation of the diode. This prevents the system from working
properly for several minutes a day at certain times of the year. In most cases this
effect can be avoided by careful selection of the mounting spot.

In order to comply with the requirements of the successful installation
discussed four key factors and other criteria
into consideration.

3.2 Preferred installation sites


All buildings and constructions have a certain movement of their own. It’s
determined by the structure and material of the building. Metal structures can shift or
twist due to temperature changes. Wooden construction can expand or sh
any changes in humidity. Give preference to concrete or brick buildings. On the
other hand high structures like towers, skyscrapers or poles are always subject to
movement. Mount the support frame to walls of the building or near corners, as they
are the most stable spots. Use appropriate consoles for wall mounting. If a stand is
used on the top of
building, secure it directly to the ceiling or to the concrete cornice wherever is
possible. Do not fix stands to insulating materials as they can sl
weight of the unit and with temperature changes. Big chimneys and smokestacks
may look stable, but as their inner temperature varies they can also move. Vibration
caused by heavy traffic, trains and elevators etc. may slowly move the sy
its specified direction. Another important consideration is to provide enough space
for alignment and to have the potential for future maintenance. Consider that the
support frame is usually heavy, so the selected spot should be easily accessib

Telefon: 06

. 6-8.


E-mail: info@geodesy

http://www.

9

Sites of installation

Key factors of operation

r key issues that the site survey has to shed light on. Proper system

operation cannot be guaranteed without satisfying all of the four requirements.

The entire optical path between the two ends must be free
only means that one has to see the other side, but other

possible sources of disturbance should also be taken into consideration. For
example there might be turbulence above the roofs and other constructions, and this
can cause fraction or scattering of the beam or snow accumulation on roofs too
close to the beam can influence or even interrupt communication.

- is the key for long-term operation. Since the diameter of

the beam is limited, it is extremely important to mount the unit on a
with the possible smallest movement. This way the receiver of the remote unit
cannot get out of the beam due to the movement of the opposite head.

West orientation

- although the receiver optics are equipped with optical

protect the receiver diode from the effect of undesired light sources, direct

sunshine can cause saturation of the diode. This prevents the system from working
properly for several minutes a day at certain times of the year. In most cases this

e avoided by careful selection of the mounting spot.

In order to comply with the requirements of the successful installation
discussed four key factors and other criteria - the following matters should be taken

ed installation sites

All buildings and constructions have a certain movement of their own. It’s
determined by the structure and material of the building. Metal structures can shift or
twist due to temperature changes. Wooden construction can expand or sh
any changes in humidity. Give preference to concrete or brick buildings. On the
other hand high structures like towers, skyscrapers or poles are always subject to
movement. Mount the support frame to walls of the building or near corners, as they
are the most stable spots. Use appropriate consoles for wall mounting. If a stand is

building, secure it directly to the ceiling or to the concrete cornice wherever is
possible. Do not fix stands to insulating materials as they can slowly sink under the
weight of the unit and with temperature changes. Big chimneys and smokestacks
may look stable, but as their inner temperature varies they can also move. Vibration
caused by heavy traffic, trains and elevators etc. may slowly move the sy
its specified direction. Another important consideration is to provide enough space
for alignment and to have the potential for future maintenance. Consider that the
support frame is usually heavy, so the selected spot should be easily accessib

Telefon: 06-1-481-2050

Fax.: 06-1-481-2049

[email protected]

http://www.geodesy-fso.com

r key issues that the site survey has to shed light on. Proper system

operation cannot be guaranteed without satisfying all of the four requirements.

The entire optical path between the two ends must be free
only means that one has to see the other side, but other

possible sources of disturbance should also be taken into consideration. For
example there might be turbulence above the roofs and other constructions, and this

e beam or snow accumulation on roofs too

term operation. Since the diameter of

the beam is limited, it is extremely important to mount the unit on a stable structure
with the possible smallest movement. This way the receiver of the remote unit
cannot get out of the beam due to the movement of the opposite head.

although the receiver optics are equipped with optical

protect the receiver diode from the effect of undesired light sources, direct

sunshine can cause saturation of the diode. This prevents the system from working
properly for several minutes a day at certain times of the year. In most cases this

In order to comply with the requirements of the successful installation - including the

the following matters should be taken

All buildings and constructions have a certain movement of their own. It’s
determined by the structure and material of the building. Metal structures can shift or
twist due to temperature changes. Wooden construction can expand or shrink with
any changes in humidity. Give preference to concrete or brick buildings. On the
other hand high structures like towers, skyscrapers or poles are always subject to
movement. Mount the support frame to walls of the building or near corners, as they
are the most stable spots. Use appropriate consoles for wall mounting. If a stand is

building, secure it directly to the ceiling or to the concrete cornice wherever is

owly sink under the

weight of the unit and with temperature changes. Big chimneys and smokestacks
may look stable, but as their inner temperature varies they can also move. Vibration
caused by heavy traffic, trains and elevators etc. may slowly move the system out of
its specified direction. Another important consideration is to provide enough space
for alignment and to have the potential for future maintenance. Consider that the
support frame is usually heavy, so the selected spot should be easily accessible.