Tire Assembly

Install a Tire Assembly onto each Transport Axle Hub,
using eight 9/16-18 x 1-1/8” bolts. Torque to 90-100 ft/lbs.
Leave supports under frame to support the machine in
case of weight shift while adding components.

NOTE

Block machine wheels securely so they will not roll while
working on or under it.

Figure 2-2: Tire Assembly

Transport Axle Hub