Connection plan, Electrical installation – Lenze E94AZMP User Manual
Page 58
Advertising
![background image](/manuals/565760/58/background.png)
Electrical installation
Connection plan
l
58
EDK94AZMP45 DE/EN/FR/ES/IT 7.0
6.2
Connection plan
Use with 9400
Standard mounting
Mounting variant
1 (BK)
2 (BK)
3 (BK)
PE (GN/YE)
L1
L1
L1
L2
L2
L2
L3
L3
L3
+
+
+
L3
PE
L1
L2
F1...F3
X301
X111
X112
X302
E94APNExxxx
K1
E94AZRPxxxx
T1 T2
X11
24V 0V
E94AZMPxxxx
1 (BK)
2 (BK)
3 (BK)
PE (GN/YE)
L1 L2 L3
+
X111
E94APNExxxx
L1 L2 L3
+
L3
PE
L1
L2
F1...F3
X301
X302
K1
X11
T1
24V 0V
T2
E94AZRPxxxxE94AZMPxxxx
SSP94NF305
SSP94NF305
Fig. 6−1
Connection concept
E94AZMPxxxx
Mains filter
E94APNExxxx
9400 DC power supply module
F1 ... F3
Fuses
K1
Mains contactor