Commissioning

Before switching on

EDK94AYCEO DE/EN/FR/ES/IT 1.0

42

l

H1inbet−LESE_INB_KHB_E94AYCEO

7

Commissioning

Before switching on

(

Stop!

Before switching on the standard device with the communication module for
the first time, check the entire wiring for completeness, short circuit and earth
fault.

,

E94AYCEO communication manual (EtherNet/IP)

Here you’ll find some detailed information on the commissioning of the
communication module.