Before switching on

EDK82ZAFPC-001 DE/EN/FR 6.0

60

H1inbet-bevor

7

Commissioning

Before switching on

Stop!

Before switching on the standard device with the function module for the first
time, check...

ƒ

the entire wiring for completeness, short circuit, and earth fault.

ƒ

whether the integrated bus terminating resistor is activated at the first
and last physical node (65).