2 project download, Project download, Commissioning – Lenze EPM−H310 User Manual

Page 56

Advertising
background image

Commissioning

Project transfer to the operating unit
Project download

5

l

56

EDBPM−H310 DE/EN/FR 7.1

5.2.2

Project download

)

Note!

In the »HMI Designer« you can select whether you want to update
the firmware at the time the project is loaded.
The firmware must always be updated with the first download of a
project to the operating unit or after an update of the
»HMI Designer« planning tool.

I

Tip!

Sample projects for the operating unit can be found in the
»HMI Designer« planning tool under File

W Open... W Samples.

0

shift

F1

Esc

F2

F3

F4

F5

Help

Info

h310_007

How to download a project into the operating unit:
1. Switch on your PC and start the «HMI Designer» planning tool.
2. Switch on the operating unit:

A. Keep the enter key

0

of the operating unit pressed.

B. Switch on the supply voltage for the operating unit.
C. Let go of the enter key

0

when H310 Service Page" appears on the

display.

3. Load the desired project from the HMI Designer into the operating unit.

See HMI Designer − Getting started" Manual.

After the download, the operating unit is ready for operation and can exchange
data with other stations via the system bus.

Advertising