4 commissioning, 1 initial switch-on, Initial switch-on – Lenze EPM-H520 User Manual
Page 71: 4commissioning
Advertising
Commissioning
L
71
EDBEPM-H520 DE/EN/FR 4.0
4
Commissioning
4.1
Initial switch-on
For commissioning, the system bus must be completely wired.
$
$
$
$
Stop!
Before switching on the supply voltage:
!
Check the wiring for completeness and short circuits,
!
Check whether the bus system is terminated physically at the first and last
station.