Handling the Steps

3. Attach the chains to the customer-supplied hoist rings (M16) on the

Integrated Operations Platform and hang the other end on the hook.

4. Raise the hook slowly and move the platform to its final location.

5. Put the platform down and take off the chains. Adjust the levelness with the

feet under the platform.

6. Contact MTS Systems Corporation to arrange for installation services.

Note

If you can guarantee the safety, other tools such as a platform vehicle
and pallet jack can also be used to move the Integrated Operations
Platform to its final location.

Handling the Steps

If you purchased the steps, unload them using the proper method (see the
Integrated Operations Platform unloading for reference). Put the steps in a
suitable place and wait for an MTS field service engineer to install them.

Hoist Ring of
M16

Do not exceed 30