MAINTENANCE/SERVICE

DRAPERS (continued)

Draper Drive & Idler Rollers

Replace draper roller bearings every 500 hours or

annually.

NOTE: When tightening jam nuts at ends of idler roller,

torque to 30 - 45 ft.lbs. (40 - 60 N

m). Over-tightening

may cause thread to fail.

NOTE: At drive roller to motor connection, there is a

short "through-bore" setscrew (F) on top of setscrew

(G). When removing, be sure to engage Allan wrench

only far enough to remove setscrew (F) first, then

setscrew (G).

Installation of Draper Seals

Front edge draper seals are supplied with the header.

These are three long L-shaped pieces bolted to the

right rear header panel. Install these seals if:

Dry material accumulates inside the draper at (A),

or between draper and front track (B).

Wind raises the front edge of the drapers.

IMPORTANT: To prevent damage to drapers, do not

use front edge draper seals in wet or muddy

conditions. In these conditions, material may pack

under the seal, causing damage to the front edge of

the drapers.

To install front edge draper seals:

1. Two of the draper seals are the same length.

Position one of these at each end of the cutterbar,

with the remaining seal in the center.

2. Install seals (C) and retainer clips (D) as shown.

Locate a clip at both seal joints, with the remaining

clips spaced approximately every eighth guard bolt.

NOTE: Clips are already installed to retain the

movable left deck. Loosen these to allow installation

of draper seal.

3. Push retainer clip against draper seal and tighten

hardware to lock in position. Draper seal must not

touch draper, but clearance is not to exceed 3/16

inch (4.5 mm).

FRONT EDGE DRAPER SEALS

AND RETAINER CLIPS

INSTALL DRAPER SEALS TO PREVENT

DRY MATERIAL ACCUMULATION