Unloading & assembly – MacDon 922 User Manual

Page 75

Advertising
background image

Form # 46620

Issue 01/06

73

INSTALL SIDE DEFLECTORS

A

B

C

D

UNLOADING & ASSEMBLY

INSTALL BREATHER IN DRIVE CASE

1. Untie plastic bag (C) and replace plug (D) in

hay conditioner gear case with breather from

bag.

INSTALL SIDE DEFLECTORS AND FINS ON HAY

CONDITIONER FORMING SHIELD ASSEMBLY

1. Insert threaded rod and welded bolt of side deflector

through hole and notch at front corner of top shield.

IMPORTANT: Do not confuse left and right side

deflectors. Welded rod (A) must be positioned to the

outside of the forming shield assembly.

2. Install two 5/8” hex nuts (B) and (C) on threaded

rod.

3. Tighten nut (B) until snug.

4. Hold nut (B) with a wrench and tighten nut (C)

securely against nut (B).

6. Install one 1/2” lock nut (D) to secure L/H link on

the welded bolt.

7. Operate handle on top shield to adjust side

deflector position. If handle is too stiff, loosen nuts (C) and (B)

and readjust.

NOTE: With hardware securing left hand link in hole (E) as

shown, side deflectors open symmetrically about the center of

the conditioner rolls. Move hardware to hole (F) to allow side

deflectors to open to maximum width. See “Hay Conditioner

Forming Shields” in Operation section.

8. For laying swaths wider than 72 inches (1830 mm), remove

deflector fins (G) from their storage position (H), and install in

holes 2 & 4 on each side of forming shield centerline. Hardware

for fins is stored at (J). Position fins approximately parallel to side

deflectors and tighten bolt securely.

NOTE:

Depending on crop conditions,

an additional 4 fins can be installed in

remaining holes, in order to produce

desired swath configurations. Fins are

available from your dealer.

INSTALL BREATHER IN

CONDITIONER GEAR CASE

D

C

SIDE DEFLECTOR CONTROL

Advertising
This manual is related to the following products:

912