Bus Splicing

Power Bus

A T T E N T I O N

A T T E N T I O N

This procedure requires contact with medium

voltage components. To avoid shock hazards, lock

out incoming power before working on the

equipment. (See Power Lockout Procedure, page
5-3). Verify with a hot stick or appropriate voltage

measuring device that all circuits are voltage free.

Failure to do so may result in severe burns, injury

or death.

1) The power and ground bus splice kit can be found in a package

mounted to the front of the shipping skid.

I M P O R T A N T

I M P O R T A N T

Verify that the structure series numbers on the splice

kit package match the structure series number found

on the cabinet nameplate (see page 1-2 for details
regarding the nameplate).

2) Refer to Access to the Power Bus, page 2-6 for Standard Enclosure

and Page 3-8 for ArcShield Enclosure.

3) For a

1200A power bus, assemble the splice bars as shown in Figure

2.20. Tighten the nuts to 48 ft·lb (65 N·m).

For a

2000A power bus, assemble the splice bars as shown in Figure

2.21. Tighten the nuts to 48 ft·lb (65 N·m).

I M P O R T A N T

I M P O R T A N T

Attach the bus links to the cabinet on the left side

first - as viewed from the front of the unit.

I M P O R T A N T

I M P O R T A N T

Always place the bus clamps on the rear side of each
main horizontal bus or splice bar, as viewed from the

front of the unit. (See Figure 4.1 or 4.2).