Migration process – flow chart, Trusted – Rockwell Automation T80015 Application Note Trusted SC300E Migration Process User Manual

Page 16

Advertising
background image

Trusted

TM

AN-T80015

Issue 01 Apr 08

AN-T80015

Page 16 of 16

Migration Process – Flow chart

Obtain ‘As

Operational’ system

file

Debug System

Trusted

fault flags

Application logic

Board definitions

Identify

Hardware

Create ini file + hot

repair associations

SC300E

fault flags

Swap MPPs for 8161 Bridge modules

Set links for each chassis, remember Trusted chassis is No1, first SC300E is No2

Fit load resistors to Chassis 2 5v supply to compensate for low current drawn by Bridge modules

Hardware Upgrade

Chassis 1 = Trusted controller chassis

What was SC300E chassis 1, is now logical chassis 2

Communication, Modbus settings

SC300E I/O modules have the option of 3-2-1 or 3-2-0. make sure the correct one is selected.

TM117-DMX TMs must appear in the list before any SC300E I/O modules

Set chassis / slot definitions

Create and wire up tags for faults on the SC300E chassis, eg. Slice, internal power, field power,

watchdog etc

Timers issues

Mirror existing system by using ladder logic or start again with FBD

Register mapping

SOE – duplicate tags required

System sizing – mounting of controller, is there room in an existing cabinet?

If in a test or demo system what test panels are needed for inputs and outputs?

Cables and lengths required

In many instances the system will have had software modified and archived without updating the

operational or as-built files. It is very important to base the migration on up to date information to

avoid nasty surprises on site

Identify / create

Registers,

Discretes and Tags

Create spreadsheet of tags, discretes, registers etc in Excel, then create library in Trusted Toolset

Create and wire up tags for faults on the Trusted controller chassis, eg. Expander, Bridge and

comms modules

Scope of Supply

Test setup or full plant upgrade.?

What Communication links are required. (Peer-to-Peer, DCS, DMX, OPC etc.

How many Trusted controllers required. (cannot communicate with SC300E directly with Peer-to-Peer

so all linked systems must be upgraded)

Pre-upgrade tests

Go through the test procedure on the existing system before making any changes to give you a

performance benchmark to test the system against after the upgrade is completed