Tweco 6000GST Cutting Systems User Manual

Page 38

Advertising
background image

SERVICE

5-8

Manual 0-2690

2. To test the Torch Leads for insulation breakdown

use the following procedure:

a. Connect the Hi-Pot Tester between the posi-

tive pilot lead and the negative lead fittings.
The fitting on the other end of the Torch Leads
must be separated (isolated) from each other.

b. Increase the output of the Hi-Pot Tester to a

maximum of 2500 VAC.

• If the voltage drops to 0 VAC or leakage

current is detected, then the insulation be-
tween the Torch Leads is breaking down
and the Torch Leads must be replaced.

• If the Torch Leads passes the test, then pro-

ceed to Step 3.

3. Visually check that the control wires, pilot lead

connection, and negative lead connections are
properly connected and in good condition (no
shorts or arcing).

• If problems are evident, repair or replace as

required.

• If there are no visual problems, then proceed

to Step 4.

4. Check the pilot lead, negative lead and control

wires for opens from one end of the torch leads to
the other.

• If open, replace leads or open component

of the Torch Leads Assembly.

• If not open, then proceed to Step 5.

5. Check the pilot and control wires for shorts to

other components in the Torch Leads.

• If shorted, then replace Torch Leads.

• If not shorted, then proceed to Step 6.

6. Carefully reassemble the components and recheck

the completed assembly per paragraph ‘B’, Step
3 to confirm that the components have been prop-
erly assembled.

This completes the checks for the proper operation of the
Torch Head and Torch Leads.

Advertising