A 1/8--in. (3.2 mm) NPT plugged tapping, accessible for test gauge
connection, must be installed immediately upstream of the gas

supply connection to the gas valve.
When installing the gas supply line, observe local codes pertaining

to gas pipe installations. Refer to the NFGC NFPA 54/ANSI

Z223.1 latest edition (in Canada, CAN/CGA B149.1).
NOTE: In the state of Massachusetts:

1. Gas supply connections MUST be performed by a licensed

plumber or gas fitter.

2. When flexible connectors are used, the maximum length

shall not exceed 36 in. (915 mm).

3. When lever handle type manual equipment shutoff valves

are used, they shall be T--handle valves.

4. The use of copper tubing for gas piping is NOT approved

by the state of Massachusetts.

In the absence of local building codes, adhere to the following
pertinent recommendations:

1. Avoid low spots in long runs of pipe. Grade all pipe 1/4 in.

(6.35 mm) for every 15 ft (4.6 m) of length to prevent traps.

Grade all horizontal runs downward to risers. Use risers to
connect to heating section and to meter.

2. Protect all segments of piping system against physical and

thermal damage. Support all piping with appropriate straps,

hangers, etc. Use a minimum of one hanger every 6 ft (1.8
m). For pipe sizes larger than 1/2 in., (12.7 mm) follow
recommendations of national codes.

3. Apply joint compound (pipe dope) sparingly and only to

male threads of joint when making pipe connections. Use

only pipe dope that is resistant to action of liquedfied
petroleum gases as specified by local and/or national codes.
Never use Teflon tape.

4. Install sediment trap in riser leading to heating section (See

Fig. 7). This drip leg functions as a trap for dirt and

condensate.

5. Install an accessible, external, manual main shutoff valve in

gas supply pipe within 6 ft (1.8 m) of heating section.

6. Install ground--joint union close to heating section between

unit manual shutoff and external manual main shut--off

valve.

7. Pressure test all gas piping in accordance with local and

national plumbing and gas codes before connecting piping
to unit.

NOTE: Pressure test the gas supply system after the gas supply
piping is connected to the gas valve. The supply piping must be
disconnected from the gas valve during the testing of the piping
systems when test pressure is in excess of 0.5 psig. Pressure test the
gas supply piping system at pressures equal to or less than 0.5 psig.
The unit heating section must be isolated from the gas piping
system by closing the external main manual shutoff valve and
slightly opening the ground--joint union.

FIRE OR EXPLOSION HAZARD
Failure to follow this warning could result in personal injury,

death and/or property damage.
--Connect gas pipe to unit using a backup wrench to avoid

damaging gas controls.

--Never purge a gas line into a combustion chamber. Never

test for gas leaks with an open flame. Use a commercially

available soap solution made specifically for the detection of

leaks to check all connections.

--Use proper length of pipe to avoid stress on gas control

manifold.

--If a flexible connector is required or allowed by authority

having jurisdiction, black iron pipe shall be installed at

furnace gas valve and extend a minimum of 2 in. (51 mm)

outside furnace casing.

--If codes allow a flexible connector, always use a new

connector. Do not use a connector which has previously

serviced another gas appliance.

!

WARNING

8. Check for gas leaks at the field--installed and

factory--installed gas lines after all piping connections have

been completed. Use a commercially available soap solution
made specifically for the detection of leaks (or method

specified by local codes and/or regulations).

OUT

TEE

NIPPLE

CAP

IN

C99020

Fig. 7 -- Sediment Trap