Leveling the Drill

Box Alignment Adjustments

Pull Bar Adjustments
Refer to Figure 10

With the drill lowered to the ground and completely
unfolded the tongue slide on the tongue should be
back against the stop on the tongue. Adjust the pull
bars length so drill boxes are in line with one anoth-
er and parallel to the back edge of the main frame.

Drill Adjustments
Refer to Figure 11

Put the transport pins in storage position.

Slowly lower the drill until it is on the ground and the
main frame top slide cylinder is fully extended. Pull
the drill forward a few feet to make sure that the
transport and the gauge wheel tires have equal firm
contact with the soil.

Refer to Figure 12

Unfold the drill on a level seedbed typical to your
soil conditions.

At the top of both vertical tubes on the transport
frame is a threaded stud and jam nut. Make sure
both studs have approximately the same length of
threads extending above the jam nut (approximate-
ly 3”) for most planting conditions. Adjustments may
be required.

11284

10671

10672

Figure 10

Pull Bar Adjustment

Figure 11

Top Slide Cylinder

Figure 12

Threaded Stud

Jam Nut

3”

Approx.