Ups initial startup – Dell UPS 1920R User Manual

Page 32

Advertising
background image

32

|

Installation

NOTE:

A separate contact must simultaneously cause UPS input AC power to be removed.

5

Connect the switch or circuit to the REPO connector on the UPS rear panel using insulated
0.75 mm

2

–0.5 mm

2

(18–20 AWG) wire.

Optional.

If you are daisy-chaining the REPO function with another UPS, connect the REPO port

labeled “OUT” to the REPO port labeled “IN” on the next UPS. Continue for each UPS. On the
last UPS in the daisy-chain, connect a REPO connector (without a jumper) in the REPO port
labeled “OUT.”

6

Verify that the externally-connected REPO switch is not activated to enable power to the UPS
output receptacles.

7

Continue to the following section, “UPS Initial Startup.”

UPS Initial Startup

To start up the UPS:

1

Verify that the internal batteries are connected.

2

If an optional EBM is installed, verify that the EBM is connected to the UPS.

3

Verify that the power input to the UPS has adequate upstream overcurrent protection:

Table 1. Minimum Upstream Circuit Breaker Rating

UPS Output Power

120V

208V

230V

1000W

15A

15A

1500W (at 100V)

1920W

20A

15A

2300W (at 100V)

2700W

30A

20A

16A