SECTION VIII-FRAME INSTALLATION

[FIG. 37]

[FIG. 36]

A. SCREW SPLINE

(CONT.)

PAGE 27

FD

FD

FD

FD

FD

PERIMETER

JAMB

FD

1/2"± SHIM

AS REQUIRED

STEP 4) ANCHORING THE HEAD

For D.L.O.'s 22" and narrower, the anchors must be spaced 2" from the

jamb and vertical members. Also another anchor 4" from the intermediate

vertical is required. For D.L.O.'s wider than 22", the outside anchors must

be spaced in a similar manner and all center anchors must be located at

16" on center Maximum. See figures 36 and 37 below for anchor

placement. These are general anchor location guidelines. Size, space,

and embedment of anchors as required to meet structural load.

FD

INTERMEDIATE

VERTICAL

16" MAX.

GREATER THAN 24"

525 IMPACT

2"

2"

2"

LESS THAN OR EQUAL 22"

16" MAX.

16" MAX.

2"

DPS 1/2004

2"

2"