SECTION IX - GLAZING

C

[FIG. 69]

B

D

[FIG. 70]

C

B

E

E

DPS 1/2004

PAGE 40

(CONT.)

STEP 6) GLASS INSTALLATION

A) Make sure that the HWD1 is installed per the instructions in figures

66-68 on page 39.

B) Position the glass on the exterior of the frame without the
removable glass stop installed. Shift the glass into the deep pocket to
begin the installation.

C) Swing the opposite edge of the glass around to align the glass with

the glazing pocket.

D) Slide the glass into the shallow glazing pocket so that an equal

amount of glass bite is on each side of the DLO.

E) Lift the glass straight up into the head or horizontal, and insert the

setting blocks at the predetermined 1/4 or 1/8 point locations. Lower

the glass back down onto the setting blocks and ensure that the glass

is still centered in the DLO. Ensure that the interior glazing gasket is
not rolled out of the gasket track.

F) Snap on the removable glass stop and install the exterior glazing

gasket. See figure 71 on page 41 for exterior gasket installation.
See figures 69 and 70 below for glass installation.

525 IMPACT

Advertising