SECTION VIII-FRAME INSTALLATION

[FIG. 45]

B. SHEAR BLOCK

PAGE 32

(CONT.)

SUBSILL

CONDITION

ASSEMBLED

FRAME

Because of the design of the shear blocks for the 525 system, EFCO

recommends that the shear block framing be used in punched

openings only. It would be possible to stack modules side by side in

a longer run. However, the last module could not be installed without

an extremely large caulk joint at the jamb of the last module installed.

For this reason, the shear block framing system should be used for

openings where the frame can be fully assembled and positioned into

the opening as a single unit.

STEP 1) INSTALLING SHEAR BLOCK FRAMES

STEP 2) SHEAR BLOCK FRAME ASSEMBLY

Begin the installation process by assembling the shear block framing

as shown in figure 11 on page 14. Once the unit has been

assembled, position the unit to the exterior of the subsill. Ensure that

the subsill has been installed and sealed correctly according to the

instructions on pages 20-25.