Snapping the snap-in filler, Fig. 42] [fig. 41, Step 9) snapping the snap-in filler – EFCO 945 Series User Manual
Page 34: Con't)

945 QUICKSET
SEAL AS REQUIRED. SEE FIG.
34-35 PAGE 29.
8309
8308
8308
8309
PAGE 32
The same action is required for
structural glazed mullions also.
[FIG. 42]
[FIG. 41]
When completely snapped, the
filler should be flush with the
interior and exterior legs of the
vertical.
KDE 11/2003
To snap the snap-in filler, place the ladder in the subsill and align the snap-in
filler with the intermediate vertical, ensuring that the ladders are as tight together as
possible before continuing. Using a rubber mallet, gently tap the filler into place if
necessary. Work from the head to the sill, verifying that the ladder is completely
engaged before anchoring the head. See Figure 42.
STEP 9) SNAPPING THE SNAP-IN FILLER
INCLUDES CAPTURED AND STRUCTURAL GLAZED MULLION SYSTEMS
SECTION VIII - INSTALLATION
(CON'T)
2 1/2"