• Confirm that the equipment received agrees with the

shipping documents.

• Confirm that the shipping documents agree with the Purchase

Order (P.O.). Refer to the product drawing submitted for the order,

as necessary.

• Confirm that the document package, consisting of a copy of the

IOM, the handrail, ladder, leg and brace installation drawings,

and the electrical connection diagram, has been received with

the shipment.

• If it is determined that modules/assemblies or any other equipment

specified on the P.O. has not been delivered, and is not accounted

for in the shipping documentation, contact AAF International

immediately at 800.477.1214.

The shipment will consist of assembled modules and some

loose parts for attachment at the jobsite, and will include the

following components:
1. Fully assembled plenum, housing and hopper modules.
2. Support structures including leg and bracing assemblies. See

drawings included with shipment for the proper number of parts.

3. Compressed air manifold connection kits for multiple modules.
4. One pulse control assembly for each unit.
5. Filter bags and cages. These filter elements may be shipped and

received separate from the other listed components.

6. Safety hand rails for standard plenum style units.
7. Safety ladder and cage assembly
8. Hardware kit
9. Caulk

NOTE: Anchor bolts for bolting the equipment to the foundations and

hardware for connecting the inlet and outlet ducts are not included

with the Millennium and must be supplied by others.

Optional components such as hopper discharge devices, gauges and

other ancillary equipment may also be included in the shipment.

Consult the P.O. and shipping documents to confirm.
1.3 Assembly

The Millennium has been designed specifically to minimize the

amount of jobsite assembly required. Consult with an experienced

rigger for an accurate estimate of the time and equipment that will be

required. All jobsite assembly will be limited to bolting components

together. NO WELDING WILL BE REQUIRED. Following is an outline

of the assembly required for a standard Millennium. See Figure 1 for

details of the Millennium:

1. Assemble Leg & Brace structure.
2. Seal with caulk and bolt together each adjoining module

(if multiple modules have been supplied).

3. Raise each module/assembly, and then attach and anchor to the

support legs and bracing structure.

4. Install the safety ladder.
5. Install the safety railing.
6. Install compressed air manifold interconnection kit(s) (if multiple

modules have been supplied).

7. Install compressed air manifold customer supplied

condensate drain(s).

8. Connect compressed air supply to the compressed air manifold.
9. Mount and wire the pulse control.
10.Attach inlet and outlet air ducts.
11. Install the filter elements.
12.Install optional components.
Detailed instructions regarding each of these operations are provided

in subsequent sections of this manual.

Figure 1. Millennium Components

NOTE: The modules will normally be bolted together prior to

attaching the legs, handrailing, and ladder.

Safety

Railing

Access

Ladder

Legs &

Bracing

96 Bag

Module

144 Bag

Module

Advertising