For Initial Installation or Service

1. Open roof doors for access to bags (see Section 3.9).
2. Remove pulse pipes as follows:

a. Loosen the bulkhead coupling to allow the pipe to slide out.
b. Remove hairpin from the opposite end of the pipe.
c. Lift the pulse pipe assembly to clear support pin and slide the

pulse pipe away from the supply pipe until it has disengaged.

Lift and remove.

3. If performing service:

a. Remove cage/venturi assembly.
b. Remove the bag by collapsing the bag cuff into a half moon

shape as shown and lifting out.

NOTE: On the initial installation, cage/venture assemblies and

bags are shipped loose.

4. Install new bag as follows:

a. Insert the closed end of the bag through the tube sheet hole

until the bag cuff is near the tube sheet.

b. Collapse the bag into a half moon shape and insert into the

tube sheet as shown.

c. Snap the bag cuff into position making sure the center groove

of the cuff seals properly at the tube sheet.

5. Insert the cage/venturi assembly into the installed bag. The

cage top should fit snugly on top of the bag cuff.

6. Repeat steps 4 and 5 until all of the bags and cage/venturi

assemblies have been installed.

7. Re-install the pulse pipe assemblies by reversing step 2 and

verify that the pulse holes are pointed down and centered over

the bags.

8. Close the roof doors and secure the latches.

NOTE: If installing pleated bags, do not deform the bag cuff since

this may result in damage to the bag. Instead, the lower flange of

the cuff should be lightly lubricated with a liquid soap solution and

the cuff should be firmly pressed into the tube sheet until it snaps

into position.

Figure 6.

Tube Sheet

Pulse Hole

See Step 2a

Pulse Pipe Support

Air Supply Pipe

Coupling Pulse Pipe Removal See Step 2B

Installation See Step 7

Cage & Venturi Assembly

Pulse Pipe Support

Bag Assembly

Bag Cuff

Tube Sheet

Bag Installation or

Removal View

7

Advertising