MODULEX EXT 321, 481, 641, 802, 962, 1123 BOILERS

Installation, Operation & Maintenance Manual

Installing the Pressure Relief Valve and Other Components

1. Attach manifold to the outlet supply connection on the boiler via the flanged connections.

2. Cut the flow switch for 2-1/2” pipe, as directed in the flow switch paddle packaging. For

installations expecting less than a 10 gpm flow, the switch must be adjusted as follows:

a) With no flow, turn adjustment screw on the switch counter-clockwise until the switch

trips.

b) Then turn screw 1/2 turn clock-wise and continue installation.

3. Connect the following components to the tapped holes in the manifold assembly (see

Figure 3-15):

• 3/4” Pressure Relief Valve
• Flow Switch
• Pressure/Temperature Gauge

4. Check to ensure that all components are securely tightened and that the flow switch

paddle moves freely without interference.

5. Locate the BMM module, with the “FL” label, at the unit front (Figure 3-16) and remove

the black jumper wire from the terminals of the connector shown in the detail of Figure
6. Connect the two flow switch wires to the two terminals. Flow switch wires have no
polarity, so can be inserted without regard to position.

Figure 3-16: BMM Location and Flow Switch Connection

3.13 Determination of Primary Boiler Pump Or Boiler System Pump

The following table gives an indication of the pump’s flow rate in function of the

∆t

of the

primary circuit if the installation has a mixing header.

The size of the pumps must be determined by installers or technical engineers according to
boiler data and system design.

Remove this black jumper and

insert the two wires from the flow

switch into terminal connector.