Table 6-1, He- 111 − scheduled maintenance – AERCO SWDW68 U-Tube Double-Wall Heaters w/ECS User Manual

Page 42

Advertising
background image

HE-

111 − SCHEDULED MAINTENANCE

Rev B Mar 2013

6-4

5. If there is evidence of scale build-up, disconnect the conduit and electrical power lines from the pump

and service or replace it, as necessary.

6. If there is no evidence of scale build-up on the recirculation pump, reinstall it and reconnect the wiring

and flanges.

Table 6-1. Recommended Maintenance Schedule

Maintenance Check

Week

(6.3)

Month

(6.4)

Quarter

(6.5)

Six Months

(6.6)

Year

(6.7)

Tube Leak

Control Valve Leak

Vacuum Breaker(s)

Shell Solids*

Over-temperature Switch Alarm

Temperature Controller

Actuator Adjustment

Steam Strainer

Over-temperature Switch

Temperature Sensor

Recirculation Pump

* Perform the first test for shell solids upon completion of the first three months of heat exchanger

operation. Depending upon the results (see 6.4.1, Step 5), repeat this test quarterly, semi-
annually or annually.

Advertising