6 recirculation pump replacement, He- 111 − corrective maintenance, Caution – AERCO SWDW68 U-Tube Double-Wall Heaters w/ECS User Manual

Page 70

Advertising
background image

HE-

111 − CORRECTIVE MAINTENANCE

Rev B Mar 2013

8-16

CAUTION

Ensure that the replacement linkage assembly, adapter and scale are identical to those
removed in previous steps. Also, ensure that the linkage pin (Figure 8-6) is set to the
proper position for the Control Valve size. Failure to observe this precaution may
result in improper Control Valve operation.

65. Using a new gasket (29), position the replacement linkage assembly on the Valve top (21). Secure

the linkage assembly to the Valve top using the previously removed cap screws (29).

66. Install the indicator plate on the Valve shaft (16) with the curved end facing upward (Figure 8-4)

67. Attach the Valve shaft (16) to the linkage adapter by rotating the shaft counterclockwise (as viewed

from above). If the Valve shaft cannot be turned by hand, use an open-end wrench to turn the
“double-nuts” on the shaft until it engages the linkage adapter threads. Insert the shaft into the linkage
adapter until the hex nuts (17) are snug against the indicator plate.

68. Press down on the Valve shaft (16) to compress the pilot spring (10) in the Valve body.

69. With the pilot spring compressed, verify that the indicator plate is aligned with the “0” (zero) on the

scale (28). If necessary, rotate the Valve shaft until the plate is aligned with “0”.

70. Replace the Actuator using steps 50 through 57, above.

8.2.6 Recirculation Pump Replacement

The recirculation pump is required to assure proper heat exchanger operation and has an expected
service life of five years. The pump is installed in the recirculation piping (see Figure 8-7) to continuously
circulate domestic water through the heat exchanger, even when there is no DHW demand.

AERCO

STEAM INPUT

CONDENSATE OUTPUT

SHELL ENCLOSING THE

TUBE BUNDLE

COLD WATER

INPUT

HOT WATER OUTPUT

CONTROL BOX

RECIRCULATION

PIPING

RECIRULCATION

PUMP

TOP HEAD

BOTTOM HEAD

CXT-E CONTROL
VALVE

CXT-E ACTUATOR

PLUGGED DRAIN

POWER SWITCH

RELIEF VALVE

Figure 8-7. Recirculation Pump Mounted in Recirculation Piping

Use the following procedure to replace the recirculation pump:

1. Turn OFF both the external power circuit breaker to the DW-series heat exchanger and the power

switch on the side of the Control Box.

2. Close all stop valves in the Steam Input and Condensate Output lines.

Advertising