FIGurE 10: stanDarD BOIlEr PIPInG

standard Piping

Figure 10 shows typical boiler system connections on a single zone system. Additional information on hydronic system

design may be found in the I=B=R Guide RHH published by the Air-Conditioning, Heating and Refrigeration Institute

(AHRI). The components in this system and their purposes are as follows:

VII system Piping

WARNING

• INSTALL BOILER SO THAT THE ELECTRICAL COMPONENTS ARE PROTECTED

FROM WATER (DRIPPING, SPRAYING, RAIN, ETC.) DURING APPLIANCE
OPERATION AND SERVICE (CIRCULATOR REPLACEMENT, ETC.).

• OPERATION OF THIS BOILER WITH CONTINUOUS RETURN TEMPERATURES

BELOW 120°F CAN CAUSE SEVERE HEAT EXCHANGER CORROSION DAMAGE.

• OPERATION OF THIS BOILER IN A SYSTEM HAVING SIGNIFICANT AMOUNTS OF

DISSOLVED OXYGEN CAN CAUSE SEVERE HEAT EXCHANGER CORROSION
DAMAGE.

• DO NOT USE TOXIC ADDITIVES, SUCH AS AUTOMOTIVE ANTIFREEZE, IN A

HYDRONIC SYSTEM.

• PIPE RELIEF VALVE DISCHARGE TO A SAFE LOCATION. THE RELIEF VALVE

MAY DISCHARGE SCALDING HOT WATER.

• DO NOT INSTALL A VALVE IN THE RELIEF VALVE DISCHARGE LINE.
• DO NOT MOVE RELIEF VALVE FROM FACTORY LOCATION.
• DO NOT PLUG RELIEF VALVE DISCHARGE. BLOCKING THE RELIEF VALVE MAY

RESULT IN BOILER EXPLOSION.