Crown Boiler TWZ175 User Manual

Page 15

Advertising
background image

13

1) Relief valve (Required) - Mount the relief valve on the top left side of the boiler as shown in Figure 10 using the 3/4”

nipple provided. The relief valve shipped with the boiler is set to open at 30 psi. This valve may be replaced with one

having a pressure up to the “Maximum Allowable Working Pressure” shown on the rating plate. If the valve is replaced,

the replacement must have a relief capacity in excess of the DOE heating capacity for the boiler.

Pipe the discharge of the relief valve to a location where water or steam will not create a hazard or cause property damage

if the valve opens. The end of the discharge pipe must terminate in an unthreaded pipe. If the relief valve discharge is not

piped to a drain, it must terminate at least 6 inches above the floor. Do not run relief valve discharge piping through an

area that is prone to freezing. The termination of the relief valve discharge piping must be in an area where it is not likely
to become plugged by debris.

2) Circulator (Required) - Figure 10 shows the ideal location of the circulator which is in the supply piping immediately

downstream of the expansion tank. A less ideal, but acceptable, location for most residential circulators is in the return (if

this is done, be sure that adequate clearance exists to open the door.

3) Expansion Tank (Required) - If this boiler is replacing an existing boiler with no other changes in the system, the

old expansion tank can generally be reused. If the expansion tank must be replaced, consult the expansion tank

manufacturer’s literature for proper sizing.

4) Fill Valve (Required) - Either a manual or automatic fill valve may be used. The ideal location for the fill is at the

expansion tank.

5) Automatic Air Vent (Required) - At least one automatic air vent is required. Manual vents will usually be required in

other parts of the system to remove air during initial fill.

6) Low Water Cut-Off (Required in some situations) - A low water cut-off is required when the boiler is installed above

radiation. In addition, some codes such as ASME CSD-1, require low water cut-offs. Codes may also require that this

low water cut-off have a manual reset function. The low water cut-off may be a float type or probe type, but must be

designed for use in a hot-water system. The low water cut-off should be piped into the boiler supply just above the boiler

with no intervening valves between it and the boiler.

Use a low water cut-off that breaks the 120 VAC supply to the boiler. Do not attempt to wire a 24-volt low water cut-off

into the boiler factory wiring.

7) Manual Reset High Limit (Required by some codes) - This control is required by ASME CSD-1 and some other codes.

Install the high limit in the boiler supply piping just beyond the boiler with no intervening valves. Set the manual reset

high limit as far above the operating limit setting as possible, but not over 240°F. Wire the control to break the 120 VAC

electrical supply to the boiler.

8) Flow Control Valve (Required under some conditions) - The flow control valve prevents flow through the system unless

the circulator is operating. A flow control valve may be necessary on converted gravity systems to prevent gravity

circulation. Flow control valves are also used to prevent “ghost flows” in circulator zone systems through zones that are

not calling for heat.

9) Isolation Valves (Optional) - Isolation valves are useful if the boiler must be drained, as they will eliminate having to drain

and refill the entire system.

10) Drain Valve - The drain valve is shipped in the boiler parts bag. Install it in the tee on the boiler return as shown in

Figure 1.

IMPOrtant

tHE 1 1/2” PluGGED taPPInG On tHE BOttOM rEar sEctIOn Is

PrEsEnt FOr ManuFacturInG PurPOsEs OnlY. DO nOt attEMPt

tO usE tHIs taPPInG as a rEturn cOnnEctIOn.

Advertising
This manual is related to the following products: