7, INSTALLATION

The exchange can be installed in any of three ways; (1) rack mounting, (2) wall mounting, and (3) desk-top

installation.

7.1. Rack younting

A) Elevated Operating Ambient - If installed in a closed or multi-unit rack assembly, the operating ambient

temperature of the rack environment may be greater than room ambient. Therefore, consideration should
be given to installing the equipment in an environment compatible with the maximum ambient temperature
(Tma) specified by the manufacturer.

B) Reduced Air Flow - Installation of the equipment In a rack should be such that the amount of air flow

required for safe operation of the equipment is not compromised.

C) Mechanical Loading - Mounting of the equipment in the rack should be such that a hazardous condition is

not achieved due to uneven mechanical loading.

D) Circuit Overloading - Consideration should be given to the connection of the equipment to the supply circuit

and the effect that overloading of the circuits might have on overcurrent protection and supply wiring.
Appropriate consideration of equipment nameplate ratings should be used when addressing this concern.

E) Reliable Earthing - Reliable earthing of rack-mounted equipment should be maintained. Particular attention

should be given to supply connections other than direct connections to the branch circuit {e.g. use of power
strips)."

The Exchange can be mounted on the CR-273 or CR-413 or standard EIA 19" Equipment rack.
These racks, when fully equipped with exchanges, can provide the following capacity of stations: 128 stations
for one CR-273, 192 stations for one CR-413, and 1,280 stations for seven CR-413s.

For the CR-273 and CR-413 Equipment rack assembly or BU-412 Blower unit Installation, read the installation

manual supplied with the rack.

Note

When installing the blower units, terminal

boards, and exchanges, lay the equipment
rack down face-up to do installation work

safely. Since the blower unit is installed from

the inside of the rack, be sure to install it first,

before mounting the other components.

7.1.1. Setting space

For maintenance works, allow much space

between the wall and Equipment rack.

7.1,2. Caution when Installing the unit

caution

block the fan exhaust vent. Doing so may cause heat to build up inside the

unit and result in fire.

Do not stack up 3 Exchanges or more. If 2 or more
Exchanges are mounted in the Equipment rack, be

sure to mount the perforated panel of 1 U size {PF-
013B) or more above and below every 2 Exchanges.

Using the supplied rack mounting screws, install the

terminal board in a location that facilitates wiring and

maintenance work, taking into consideration the

direction of cable entry into the rack.

Exchange

Equipment rack

Perforated panel

7