Auto system with mpc operational test – Dukane ULTRASONIC GENERATOR/POWER SUPPLY 403-573-02 User Manual
Page 36
 
Page 3
Page 30
iQ Series,
Auto User’s Manual
Section 4 –System Operation
Dukane Manual Part No. 403-573-02
Page 3
Page 30
iQ Series,
Auto User’s Manual
Section 4 –System Operation
Five fault conditions are monitored by the iQ 
Auto system for Any Fault: 
•
Average Overload
(Automatically resets on next cycle, or until an 
activation of Fault Reset Input)
•
Peak Overload
(Resets same as Average Overload)
•
Overtemperature
(Automatically resets on cool-down)
•
Power Not OK
(AC line voltage under 180VAC)
•
Frequency Overload
(Automatically resets on next cycle, or until an 
activation of Fault Reset Input)
iQ
Auto System with MPC
Operational Test
Step 1. Verify that the system installation (with the MPC
option) is completed and all cables are connect-
ed.
Refer to the iQ Auto installation instructions in 
Section 3, if needed.
Refer to Section 6 - Automation Interface - for in-
formation on wiring system controls, if needed.
Step 2. After completing Step 1, activate line power to the
standard iQ Auto system.
Normal Condition:
The POWER STATUS
LED
on the iQ Auto front
panel should light up GREEN.
The MPC module SYSTEM STATUS
LED
should
light up GREEN.
The system is ready to operate when both status
LED
s
light up GREEN.
Troubleshooting Abnormal iQ Auto Sys-
tem Conditions
RED - If the POWER STATUS
LED
lights
up RED, check line voltage level.
GRAY - If the POWER STATUS
LED
is a
gray color (not lit), check line input.
Troubleshooting Abnormal MPC Module 
Conditions
MPC Module
SYSTEM STATUS
LED
is
ORANGE/YELLOW
(resettable fault):
•
Check for an iQ Auto overload on the previous
welding cycle.
•
Check for an invalid channel selection input
control code - selection code is greater than the 
number of installed channels.
MPC SYSTEM STATUS
LED
is RED (non-recov-
erable fault.
Check for POWER OK fault on the iQ Auto Sys-
tem.
•
Resolve any iQ Auto power problem first.
•
There could be a circuit failure in the MPC
module. If a circuit failure is discovered, return 
the MPC Module to Dukane for service.
Step 3. After completing Step 2, test ultrasound output
by activating I/O Connector Pin 12.
Normal Condition:
The system is operating properly when power is 
delivered to the attached stack.
Ultrasound Activation Connections
:
Usually an automated control system is wired 
to this control input.
Optionally - A manual switch could be wired 
to this control input.
Continued
Continued from previoius page