INSTALLATION

- 27 -

Operational Gas Inlet Pressure

With ALL other gas appliances operating, check the operational
supply pressure at the gas service isolation valve test point, see
diagram 11.1.
The nominal supply pressure for Natural Gas (G20) is 20mbar.
Turn the taps and appliances off, then disconnect the pressure
gauge.
Additionally the safe nominal maximum heat input of the
appliance can be achieved at an inlet pressure down to 15mbar.
NOTE:

The BURNER PRESSURE cannot be measured.

Gas Rate

Make sure that ALL other gas burning appliances and pilot
lights are off.
Check the gas rate using the gas meter test dial and stop
watch, at least 10 minutes after the burner has lit.
The approximate maximum gas rates are:

11.6 Range Rating

The boilers are fully modulating, therefore it is not necessary to
range rate them, however, if desired, you can adjust the boiler
in 1kW increments between 10 and maximun output of your
appliance, as follows:

a) Press and hold the ‘MODE’ and “+” button for 5

seconds. The display will change to fl ashing ‘0’.

b) Use the ‘+’ or ‘-’ button to scroll to 96.
c) Press and hold ‘MODE’ 5 seconds to confi rm.
d) The display now shows a fl ashing ‘d. 0’.
e) The part load setting is displayed in kW.

Press ‘MODE’ the max rate will be indicated, to
change the value to the desired setting, use the ‘+’ or
‘-’ button.

f) Press ‘MODE’ for 5 sec to confi rm the new setting has

been saved.

g) Press and hold ‘MODE’ and “+” to exit.

kW

m3/hr

ft3/hr

kW

m3/hr

ft3/hr

35

3.7

131

22

2.3

81.2

34

3.6

127

21

2.2

77.7

33

3.5

124

20

2.1

74.2

32

3.4

120

19

2.0

70.6

31

3.3

117

18

1.9

67.1

30

3.2

113

17

1.8

63.6

29

3.1

109.5

16

1.7

60.0

28

3.0

106

15

1.6

56.5

27

2.9

102.4

14

1.5

53.0

26

2.8

98.9

13

1.4

49.5

25

2.6

91.8

12

1.3

45.9

24

2.5

88.3

11

1.2

42.4

23

2.4

84.8

10

1.12

38.9

11.7 Heating System

Ensure that the external controls are calling for heat.
Fully open all radiator valves, fl ow control valve and bypass
valve if fi tted.
Balance the radiators as required and if fi tted adjust fl ow
control valve to give the required system differential. Turn off
all radiators that can be shut off by the user and check to see
if less than the maximum differential allowed of 20

0

C can be

achieved across fl ow and return.
NOTE: Allow the system to reach maximum temperature then
switch off the boiler by isolating from the electrical supply.
Drain the entire system rapidly whilst hot, using the drain tap
at the lowest part of the system. Fill and vent the system as
described previously in section 11.2
Lock or remove the handle from controls valve, if fi tted.
Adjust the boiler temperature controls and any system controls
to their required settings.

11.8 Completion

Ensure that the magnetic lighting instruction label is placed on
the surface of the boiler casing.
GB: It is a requirement that the “Benchmark” Installation
Commissioning and Service Record is completed and left wth
the user.
IE: it is necessary to complete a “Declaration of Conformity” to
indicate compliance to I.S.813. An example of this is given in
the current edition of I.S.813.

11.9 Instruct the User

● Demonstrate, then instruct the User about the lighting
procedure and heating system controls operation.
● Advise that to ensure the continued effi cient and safe
operation of the boiler it is recommended that it is checked
and serviced at regular intervals. The frequency of servicing
will depend upon the installation conditions and usage, but in
general, once a year should be enough.
● Draw attention, if applicable, to the current issue of the Gas
Safety (Installation and Use) Regulations, Section 35, which
imposes a duty of care on all persons who let out any property
containing a gas appliance in the UK.
● The user shall not interfere with or adjust sealed components.
● It is the Law that any servicing is carried out by a competent
person
approved at the time by the Health and Safety
Executive.
● Advise the user that, like all condensing boilers this appliance
will produce a plume of condensation from the fl ue terminal in
cool weather. This is due to the high effi ciency and hence low
fl ue gas temperature of the boiler.
● Advise the user of the precautions necessary to prevent
damage to the system, boiler and the building, in the event of
the heating system being out of use during frost or freezing
conditions.
● Advise the user that the permanent mains electrical supply
SHOULD NOT be switched off, as the built in frost protection
and pump saver program will not operate.
● Advise the User if the mains electricity and gas are to be
turned off for any long periods during severe weather, it is
recommended that the whole system, including the boiler,
should be drained to avoid the risk of freezing.
NOTE: Sealed System: Contact your installation/servicing
company as draining, refi lling and pressurising MUST be
carried out by a competent person approved at the time by the
Health and Safety Executive.
● Leave these instructions and the ‘Benchmark’ Installation,
Commissioning and Service Record with the user.