Loaded generator, Power verification – Basler Electric CBS 212A User Manual

Page 22

Advertising
background image

16

9270700990 Rev F

Loaded Generator

1.

De-energize the generator field and connect a suitably-sized jumper wire across terminals TB1-1
and 2.

2.

Perform Steps 1 through 4 of the Unloaded Generator sub-section.

3.

Remove the jumper wire from terminals TB1-1 and 2 when calibration verification is complete.

Power Verification

To verify that the CBS 212A will provide the specified boost current during short-circuit operation, refer to
the generator manufacturer’s recommended procedures for generator testing under short-circuit
conditions. If desired, final adjustment of the Output Limit Adjustment control may be made during short-
circuit testing.

Testing

CBS 212A