Installation – Flowserve LRG 16-40 User Manual

Page 16

Advertising
background image

6

Installation

– continued –

Opening terminal box

. Undo cover screws

H and remove terminal cover I. The arrow on the name plate points towards

the cover to be removed.

Terminal box

Note

When the terminal box is open it can be aligned, removed and mounted, the terminal

strips can be wired, and – if necessary – the baud rate and node-ID settings can be

changed all in a single operation.

Aligning terminal box

Terminal box open:
. Use open-end spanner A. F. 9 to loosen the fixing nut

N and turn the terminal box in the desired

direction (cable gland!).

. Re-tighten the fixing nut

N with a torque of 5 Nm.

If necessary you can take off the terminal box in order to align the electrode part. The terminal box

must be re-installed after alignment.

Removing terminal box

Terminal box open:
. Unplug the electrode wires from terminal lugs for electronic circuit board

O, functional earth L.

. Use open-end spanner A. F. 9 to unscrew the fixing nut

N. Pull electrode wires through fixing nut

N.

3. Remove terminal box. Run all electrode wires through the hole for the fixing screw (see

Fig. 6).

4. Remove the joint ring

M between the electrode and the terminal box.

Advertising
This manual is related to the following products: