ELECTRONIC TRAY, WIRING CHECK OUT

• Verify the Input and Output Connections are per wiring detail in section 3-11 for the Model being

installed.

• Verify the Input and Output TB 1 have been torqued to value below:

• Screw torque shall be 35 lbs./ in, ( 4.0 N-m) for TB 1.

• Screw torque shall be 45 lbs./ in, ( 5.1 N-m ) for Ground lug.

3-14

PBC-II BATTERY CONNECTION

• Check that BLACK & RED plug (J2/P2) from the Battery is in the Battery Jack on the electronic

Tray.

• Engage the Heater’s plugs (J5/P5) on the Model’s with battery Heaters.

• Make sure thermoprobe connectors (J3/P3) are connected.

3-15 PBC-II

POWER

UP PROCEDURE

• Check CB 1, CB 2, and CB 9 are in the “OFF” position.

• Now is the time to remove Safety Tagouts, and turn “ON” the installation Power Distribution Circuit

Breakers to “ON”.

• Check for AC Input Voltage at TB1-1, -2 to be correct for the model installed.

• Turn CB1 to the “ON” position,

• Measure the AC input voltage into the PBC-II to be proper for this Model. The Green “AC ON” LED

shall be “ON”.

• Green MB and HB LED will be “ON”.

• The Green “BYPASS” LED will turn “ON”, after about 20 seconds.

• Turn CB 9 to “ON”.

• With a Digital Voltmeter check the battery Voltage across the RED & Black plug terminals. The DC

Voltage shall be 81 to 110 VDC. If battery voltage is less than 81 VDC, replace the batteries.

• Turn CB 2 and CB 3 through CB 7 “ON”, as applicable.

• Apply the load in steps. The Green “LOAD LEVEL” LED’s will light in succession as additional load

increases.

• Unit is ready and in operation.