PBC-II BATTERY BACK-UP OPERATION TEST

• Verify the battery voltage to be 90 VDC or higher at TB1-21, -22 before performing a quick backup

test.

• Run the unit in AC mode by closing CB1, CB9 per above Section 3-14.

• Turn “CB1” to the “OFF” position.

• Note that the green LEDs for “ON UPS”, and “On ’Battery” are lit. A beeper will sound to indicate

the unit is running from battery.

• Turn CB 2 to “ON” position.

• With a Digital Voltmeter check the output Voltage to be as required.

• Apply the load in steps. The Green “LOAD LEVEL” LED’s will light in succession as additional load

increases.

• Turn CB1 to “ON” position.

• Unit is ready and in operation.

3-17 PBC-II

PAD

LAYOUT

• Use M12 or 1/2 inch Anchor Bolts for mounting PAD Plate to Concrete Pad or Roof.

• PAD Plate may be crossways to door as shown .

PBC-II LAYOUT

ILLUSTRATION 3-6