H. water supply and drain connections – Hoshizaki KM-1601SWH/3 User Manual

Page 28

Advertising
background image

28

H. Water Supply and Drain Connections
See Fig. 17, 18, and 19

WARNING

1. Water supply and drain connections must be installed in accordance with

applicable national, state, and local regulations.

2. Normal operating water temperature should be within 45°F to 90°F (7°C

to 32°C). Operation of the icemaker, for extended periods, outside of this
normal temperature range may affect icemaker performance.

3. To prevent damage to equipment, do not operate the icemaker when the

water supply is off, or if the pressure is below 10 PSIG. Do not run the
icemaker until the proper water pressure is reached.

• A plumbing permit and services of a licensed plumber may be required in some areas.
• External filters, strainers, or softeners may be required depending on water quality. Contact

your local Hoshizaki distributor for recommendations.

• Water supply pressure should be a minimum of 10 PSIG and a maximum of 113 PSIG. If

the pressure exceeds 113 PSIG, the use of a pressure reducing valve is required.

• The icemaker and condensation drain line(s), storage bin drain line, and water-cooled

condenser drain line (if applicable) must be run separately.

• Drain lines must have 1/4" fall per foot (2 cm per 1 m) on horizontal runs to get a good

flow. A vented tee connection is also required for proper flow.

• Drain lines should not be piped directly to the sewer system. An air gap of a minimum of

2 vertical inches (5 cm) should be between the end of the drain pipes from the icemaker
and condensation drain, storage bin, and water-cooled condenser (if applicable) and the
floor drain.