Step 6, secure wiring, Step 7, size and install ductwork, Installation instructions – GE MONOGRAM ZV1050 User Manual

Page 12: Step 6 secure wiring, Step 7 size and install ductwork

Advertising
background image

12

Installation Instructions

STEP 6 SECURE WIRING

• Route house wiring through the ceiling hole

and pull a length to reach the hood junction box,
approximately 6" below the support.

STEP 7 SIZE AND INSTALL

DUCTWORK

• Tape the wire to the left side of the frame

support to prevent damage during installation
and service.

• Measure from house duct flange to bottom of support

frame (Dim. A).

– Add at least 1" for duct overlap at the top.
– Subtract 1-3/4" for hood insertion into the bottom

of the frame to determine required duct length.

• Cut the 8" duct length required.
NOTE: The bottom of the duct must be external
(female) connection to the top of the hood. The
bottom end should be flared slightly, to facilitate
installation of the hood.
• Install duct up through support frames and attach

to house ducting with sheet metal screws.

• Seal the connection with duct tape.

538Dia20

Ceiling

Support

Frames

Tape

House

Wiring

Left Side

View

Advertising