STEP 1 CONSTRUCT CEILING SUPPORT

Plan the location
Determine the exact location of the vent hood.
• Use a plumb bob to check location to be sure countertop/

cooktop location below the hood will align exactly.

• The hood should project forward 1-1/2" beyond the front

edge of the cooking appliance. See illustration.

• Observe the recommended space (30") between the cooking

surface and bottom of hood.

538Dia3

Ceiling

Hood

Ducting

Centerline

Side View

Approx. 1-1/2"
Beyond Cooking
Surface

Cooktop

Countertop

31-1/2"

Hood

Front

15-3/4"

Ceiling support structure
• At the hood location, install 2 x 4 cross-framing

between ceiling joists as shown. (2x4s are required
to support the weight of the hood.)

• Arrange cross-framing in the ceiling to suit the

existing structure.

• Your ceiling joists will be like one of the following

examples.

11-1/4" Install Cross-Framing

Symmetrically About

Duct/Cooktop Centerline

7-1/4"

16" Joist

Spacing

2x4 Cross-

Framing

8" Duct

Align Duct to Center

of Cooktop

Cooktop

Outline

Top View—Ceiling Joists Parallel to Front of Hood