Step 4

: Final Installation Procedures

This section does not include details on sealing installations that incorporate a continuous air barrier system such

as house wrap or building paper in standard wood frame construction. For flashing details in this application refer

to the section, “Continuous Air Barrier Systems − Flashing the Installation”.

1. Place a bead of sealant at the wood buck to masonry

joint. See figure 12a.

2. For recessed masonry applications, Marvin recom-

mends sealing at the buck to frame joint with ap-

propriate width backer rod and sealant around the en-

tire perimeter. Finish as applicable local code dic-

tates. See figure 12b.

Figure 12: Sealing recessed masonry openings

3. In some situations such as recessed masonry

openings, you can use frame expander or other

clad accessories to finish the exterior. If this is the

case, apply a bead of sealant between the acces-

sory and the masonry at the head jamb and jamb

sections. Leave the sill portion unsealed to allow

water to escape. See figure 12c.

4. Apply a 1,−2,

(25−51)

thick bead of low expansion

foam insulation on the back side of the nailing fin,

brick mould casing or other trim. Do not apply too

much as it is possible to bow the jambs. Now insulate

loosely around the window with fiberglass insula-

tion. See figure 13.

Backer

rod

Sealant

Sealant

(c)

(b)

(a)

5. Interior and mullion trim: Install mullion trim after

interior trim or casing is applied. On Ultimate

Double Hung units, be sure to use nails and sta-

ples that are no longer than 3/4,

(19)

. Place fasten-

ers at least 1,

(25)

from the edge of interior jamb

liner.

Figure 13: Insulating the rough opening

Low

expansion

foam

Fiberglass

insulation

11