Installation and Power-On


Unpacking


Carefully unpack the NCB-1004 and verify that the following items are included:


• NCB-1004 Network Control Box

• V-PS12-5V-1 Power Supply with 2-Pin Twist Lock Connector

• Operating Instructions

Inspect the unit for any physical damage that may have occurred during shipping. Should there be any damage,
immediately contact Marshall Electronics at (800) 800-6608. If you are not located within the continental United States,
call +1 (310) 333-0606.



Installation

The NCB-1004 can be mounted in any standard EIA 19” equipment rack. If additional equipment is installed directly
above and below the NCB-1004 in a rack, adequate ventilation of the rack is required to prevent overheating.













Power-On Procedure

Plug the V-PS12-5V-1 power supply into an AC power source (100-240 V @ 50/60 Hz). Attach the 2-pin twist lock
connector to the back of the unit. The NCB-1004 will automatically turn ‘ON’ when power is supplied.

NOTE THAT THE NCB-1004 TAKES ABOUT 3 MINUTES AFTER POWER ON BEFORE IT IS FUNCTIONAL.
WAIT 3 MINUTES AFTER POWER ON BEFORE ACCESSING THE NCB-1004 VIA A NETWORK CONNECTION.