PVC Materials should use ASTM D-2564 Grade Cement; CPVC

Materials should use ASTM F-493 Grade Cement and ABS

Materials should use ASTM D-2235 Grade Cement.

If the water heater is being installed as a replacement for an

existing power vented heater in pre-existing venting, a thorough

inspection of existing venting system must be performed prior

to any installation work. Verify that correct material as detailed

above has been used, and that the minimum or maximum vent

lengths and terminal location as detailed in this manual have been

met. Carefully inspect the entire venting system for any signs of

cracks or fractures, particularly at joints between elbows and

other fittings and straight runs of vent pipe. Check system for signs

of sagging or other stresses in joints as a result of misalignment

of any components in the system. If any of these conditions are

found, they must be corrected in accordance with the venting

instructions in this manual before completing installation and

putting the water heater into service.

note: For water heaters in locations with high ambient

temperatures (above 100°F) it is recommended that CPVC or

ABS pipe and fittings be used.

4. All vent (exhaust) pipes must be pitched a minimum of a

1/4” per foot back to the water heater to allow drainage of

condensation.

InstallatIon of vent sYsteM

Before beginning installation of piping system thoroughly read the

section of this manual VENT PIPE PREPARATION.

If you are installing your system so that it vents through roof,

please refer to section titled INSTALLATION OF VERTICAL VENT

SYSTEM.

vent terMInal InstallatIon, sIdewall

1. Install the vent terminal by using the cover plate as a template

to mark the hole for the vent pipe to pass through the wall.

BEWARE OF CONCEALED WIRING AND PIPING INSIDE THE

WALL.

2. If the Vent Terminal is being installed on the outside of a finished

wall, it may be easier to mark both the inside and outside wall.

Align the holes by drilling a hole through the center of the

template from the inside through to the outside. The template

can now be positioned on the outside wall using the drilled hole

as a centering point for the template.

3. A) MASONRY SIDE WALLS

Chisel an opening approximately one half inch (1.3 cm) larger

than the marked circle.

B) WOODEN SIDE WALLS

Drill a pilot hole approximately one quarter inch (0.64 cm) outside

of the marked circle. This pilot hole is used as a starting point

for a saws-all or sabre saw blade. Cut around the marked circle

staying approximately one quarter inch (0.64 cm) outside of the

line. (This will allow the vent to easily slide through the opening.

The resulting gap will be covered up by the Vent Terminal cover

plate.) Repeat this step on inside wall if necessary.