INSTALL THE FLUE COLLECTOR

1. Collect the Flue Collector cartons. The Flue Collector

sections are labeled on the part and on the carton.
See Table 4.1 for the items needed.

2. Install Hi Temp Rope for each collector section as

shown in Figure 4.1. The rope provides the seal to
prevent flue gases from leaking from the collector.
Make certain that the rope is well under the bottom
edges of each flue collector section in order to obtain
a tight seal.

3. Place the Flue Collector sections in the positions

given in Table 4.1. These positions are numbered
from left to right when facing the front of the
boiler.

4. Fasten an angle bracket, part number GG-5005, to

the top of each Collector section with two #10 x 1/2"
(13 mm) long sheet metal screws. See Figure 4.2.

5. Insert a Long Hook Bolt, part number GG-5003,

through the angle bracket. Slip the hook end over
the tie rod. Apply a 1/4"-20 hex nut on the end of
the rod and snug against the bracket. See Figure 4.2.
Do not tighten yet.

6. Insert a Short Hook Bolt, part number GG-5004,

through the flange in the rear of the flue collector.
Catch the hook around the spacer pads at the top of
the boiler sections. Apply a 1/4"-20 hex nut on the
Bolt and snug against the flange. See Figure 4.2. Do
not tighten yet.

7. Draw the Flue Collector sections tight against the

sealing rope by tightening the nuts on the Hook
Bolts. Draw the nuts evenly, alternating tightening.

4. INSTALL THE FLUE COLLECTOR

Figure 4.2: Installing Flue Collector Sections

Figure 4.1: Applying Flue Collector Hi Temp Rope Gasket