Pre-Startup
Requirements

Airside Economizer Installation

Unit Handling
1. Hoist the damper cabinet to the

installation location with straps
positioned under the skid as shown in
Figure I-PR-12. Use spreader bars to
prevent unit damage during lifting.

2. With the damper cabinet at its final

location (near the unit), remove the
screws securing it to the skid from the
side flanges. Retain these screws for
later use.

Unit Preparation
3. The support legs are secured to the

skid, and the hanging bracket is secured
with wire ties to an inside flange near
the cabinet’s base. Remove the
C-channel collar and install it on the unit,
if not already installed.

4. Remove the roll of

1

/

8

” thick gasket

from the damper cabinet’s W-supports,
and apply it to the C-channel collar
mounted on the rear of the unit. This
gasket will provide a seal between the
damper cabinet and the unit.

5. Attach the legs (with screws provided)

to the leg brackets located on the
damper’s base.

6. Attach a field-provided clevis of

suitable strength ( >

1

/

2

” ), to each of the

corner lifting brackets through the

7

/

8

” diameter holes.

7. Attach to the clevises a means of lifting

the damper cabinet from its skid.

Unit Installation
8. Slowly raise the damper cabinet from

its skid.

9. Attach the hanging bracket across the

front of the damper cabinet. Position it
with its short flange pointing to four
o’clock, and secure it with screws
provided. See Figure I-PR-13.

10. Lift the damper cabinet and position it

such that the hanging bracket is
positioned over the unit’s C-channel
collar.

Figure I-PR-12. Proper lifting of the airside economizer.

10. Lower the damper cabinet until the

holes in its side flanges are aligned with
the holes in the C-channel collar. Install
screws removed in step 3 through the
damper cabinet’s side flanges and into
the C-channel’s corresponding holes.

11. Attach ductwork to the top and back

dampers according to local codes.

Field Wiring Connections
12. Open the damper cabinet’s door and

connect the factory-provided plug
from the actuator to the factory-
provided plug
in the unit’s filter
section.

Figure I-PR-13. Proper installation of the airside economizer option.

Installation

13. Cabinets with TRAQ™ dampers

only: Unroll the two rolls of pneumatic
tubing located inside the damper
cabinet. Route these tubes through the
cabinet’s front upper panel (0.25 dia.
holes provided). Connect them to the
two pneumatic tubes protruding from
the customer electrical connection
panel on the unit. Be sure to connect like
tubes to each other (black to black,
white stripe to white stripe).

14. Cabinets with TRAQ™ dampers

only: Locate the “bullet” sensor and
rolled up wiring in the unit’s filter
section. Route it into the damper
cabinet and insert the sensor into the
sensor mounting clip attached to
underside of one of the Traq™
dampers.