Reconnecting the ups – 3Com Powerware Uninterruptible Power System Prestige Series User Manual

Page 61

Advertising
background image

UPS Operation

55

Powerware

®

Prestige Series Installation and Operator’s Manual for IBM Applications (3000 VA) Uncontrolled Copy

Reconnecting the UPS

Use the following procedure to reinstall the UPS and transfer the critical
load from Maintenance Bypass (AC Line operation) to the UPS:

1. Reconnect the battery cabinet to the battery connector on the

UPS rear panel.

2. Switch the circuit breaker on all battery cabinets to the ON (

|

)

position.

3. Steps 4 through 8 are for changing the output voltage. The

output voltage is factory-configured for 230V. If you do not
need to change the UPS output voltage, skip to Step 9. Use the
following table to select the correct output voltage according to
your PPDM.

PPDM Model Number

UPS Voltage Selection*

5-15R PPDM 208: 120/208

208

5-15R PPDM 208: 120/240

208

5-15R PPDM 208: 120

208

5-15R PPDM 240: 120/240

Set to 220V for 110/220V PPDM output
Set to 230V for 115/230V PPDM output
Set to 240V for 120/240V PPDM output

5-15R PPDM 240: 120

Set to 220V for 110V PPDM output
Set to 230V for 115V PPDM output
Set to 240V for 120V PPDM output

5-15R/6-15R PPDM: 208

208

5-15R/6-15R PPDM: 240

240

IEC 320-C13 PPDM

Set to 220V for 220V PPDM output
Set to 230V for 230V PPDM output
Set to 240V for 240V PPDM output

*

The UPS output voltage should be set according to local mains voltage.

4. Press and hold the Output

Off button while plugging the

Y-cord of the PPDM into the power connectors on the UPS as
shown in Figure 17.

Release the Output

Off button when the alarm beeps.

All indicators flash simultaneously.

Advertising