Infinity D Power System Installation Guide: -48V Plants

H2007001

Issue 2.0, June 3, 2009

59

Install Battery VT Probes

Install Battery VT Probes without Voltage Monitoring

The QS873A weatherized VT-Probe is provided with 2-pin and 3-pin receptacles and a
1/4-inch ring terminal.

VT-Probe Connections to Controller Connection (Lead Acid)

Step

Action

1.

Insert the RJ-45 end of the 848719795 wireset into the Temp Connector on the controller.










Using voltage monitoring?

Yes – Proceed to Step 2.

No – Go to Step 3.

2.

Cut the brown voltage sense wire on the 848719795 at the 3-pin connector.